2.3Time & work, pipes & cisterns

The idea

Time and work: if a job takes a days, one day finishes 1/a of it. Add the rates of people working together.

Think of it like this: Filling a tank with taps: add the flows, and a leak is a negative flow.

Why it exists

Work, pipes and cost-of-erection problems all come from rates.

How it works

  1. Rate = 1 / days.
  2. Combined rate = sum of rates (leaks negative).
  3. Time together = 1 / combined rate.
  4. Cost = rate-per-day × time: percentage changes multiply.

Worked example: A in 10 days, B in 15 days

Rate 1/10 + 1/15 = 1/6, so 6 days together.

Now play with it

  • →Add a leak that empties in 20 days and watch the time grow.
  • →Make the leak faster than the fill and see it never finishes.
Rate of A0.1 /day
Rate of B0.0667 /day
Leak rate0 /day
Combined rate0.1667
Time together6 days
Fraction done per day166667/1000000

Add rates, not days. A leak is a negative rate. If the combined rate is zero or negative, the tank never fills.

Check yourself

A fills a tank in 10 hours, B empties it in 15 hours. Both open: time to fill

Remember: Add rates. A leak is negative. Time = 1 / combined rate.
Exam notes (the dense version)

If A finishes in a days, A does 1/a of the job per day. Add rates for people working together: time = 1 ÷ (1/a + 1/b). A pipe that fills in x hours has rate 1/x; a leak has a negative rate. Work is proportional to men × days × hours, so more men means fewer days (inverse).